Skip to main content
Submitted by admin on Thu, 08/20/2026 - 08:47
Aerial view of the Tempe Marketplace site (Photo Courtesy of Densification, Inc.)
Aerial view of the Tempe Marketplace site (Photo Courtesy of Densification, Inc.)

Project Summary/Scope:

The Tempe Marketplace property was historically used as a Municipal Solid Waste (MSW) and construction debris landfill for decades prior to the late 1990s. In 2015, the site was targeted for redevelopment as a thriving commercial and retail destination within Tempe. In order to stabilize the over 40 feet of highly variable landfill material underlying the site, a dynamic compaction program was conducted across the entirely of the development footprint. In areas to receive vertical construction, additional high-energy passes were completed to provide additional strengthening to the on-site soils. Following dynamic compaction, the new construction at the site was supported utilizing shallow foundation systems in conjunction with slab-on-grade construction. The dynamic compaction program consisted of two high-energy passes of a 20-ton weight dropped from a height of 60-feet, utilizing a 15-foot grid spacing with six drops completed at each point across the entire site. At the building locations, an additional two high-energy passes were completed using the same weight/height combination; however, 12-foot grids were used for the additional passes with six drops completed at each point. In calculating the depth of influence of the weight/height combination to be used, an n-value of 0.45 was chosen, indicative of the major component of the landfill layer being soil. When adding the four passes together, a total applied energy of 584 kJ/m3 was imparted to the landfill material.

Complementary Technologies Used: 

None

Alternate Technologies:

None

vibration_monitoring
Vibration monitoring during Deep Dynamic Compaction (Photo Courtesy of Densification, Inc.)

 

Deep Dynamic Compaction near an existing roadway (Photo Courtesy of Densification, Inc.)
Deep Dynamic Compaction near an existing roadway (Photo Courtesy of Densification, Inc.)

 

Performance Monitoring: 

Ground response (i.e. crater depth) was monitored during the course of the work, along with vibration monitoring to assess the impact on off-site structures and utilities.  Post-improvement testing consisted of plate load testing to assess the magnitude of settlement that could be expected under construction loads; the results of multiple tests indicated an anticipated post-construction settlement of less than one inch. 

Cost Information: 

The dynamic compaction work was completed on a unit rate basis of approximately $1.00/sf for the initial two passes across the site and an additional $1.25/sf for the additional two building passes; cost of the earthwork support is unavailable. 

Case History Author: 

Chris Woods, P.E., G.E., BC.GE, P.Eng, CEng MIEI, F.ASCE

Project Technical Paper: 

Woods, C.B., Shaffer, R.A., and Drumheller, S.J. (2023).  “Dynamic Compaction: A Proven Ground Improvement Alternative Method for Landfill Sites.” In proceedings for GeoCongress 2023, Los Angeles, California, March 26-29.

Title
Tempe Marketplace, Tempe, AZ
Location
Tempe, AZ
Year
2015
Contractor
Densification, Inc.
Engineer
Hoque and Associates